| Code | Document | Type | Owner | Version | Next review |
|---|---|---|---|---|---|
| IRB-POL-001 | Work Health and Safety Policy This policy sets out Ironbark Engineering's commitment to the health and safety of everyone who works at or visits its w | Policy | General Manager | 4.1 | 20 January 2027 |
| IRB-POL-002 | Quality Policy This policy states how Ironbark Engineering assures the quality of fabricated, machined and maintained work so that ever | Policy | Quality and Safety Manager | 3.0 | 4 March 2027 |
| IRB-POL-003 | Environmental Management Policy This policy sets out how Ironbark Engineering manages the environmental effects of fabrication, machining and maintenanc | Policy | Quality and Safety Manager | 2.2 | 11 November 2027 |
| IRB-POL-004 | Fitness for Work Policy This policy sets the expectation that every worker presents fit for work, free of the effects of alcohol, drugs and fati | Policy | General Manager | 2.0 | 16 February 2027 |
| IRB-PRO-001 | Hot Work Permit Procedure This procedure describes when a hot work permit is required, how it is raised, authorised and closed, and the fire preca | Procedure | Quality and Safety Manager | 3.3 | 9 April 2027 |
| IRB-PRO-002 | Isolation and Lockout Procedure This procedure sets out how machines and plant are shut down, isolated from all energy sources, locked and tested before | Procedure | Maintenance Services Manager | 4.0 | 27 May 2027 |
| IRB-PRO-003 | Job Card and Work Order Procedure This procedure describes how a job card is raised, what it must contain, how it moves through the workshops and field cr | Procedure | Engineering Office Manager | 2.4 | 22 July 2027 |
| IRB-PRO-004 | Incident and Hazard Reporting Procedure This procedure explains how injuries, incidents, near misses, hazards and environmental incidents are reported, recorded | Procedure | Quality and Safety Manager | 3.1 | 3 June 2027 |
| IRB-FRM-001 | Incident and Hazard Report Form This form is completed by the worker or supervisor for every injury, incident, near miss, hazard or environmental event, | Form | Quality and Safety Manager | 2.3 | 3 June 2027 |
| IRB-FRM-002 | Hot Work Permit This permit is completed before welding, cutting, grinding or heating outside the designated hot work bays and records t | Form | Quality and Safety Manager | 3.3 | 9 April 2027 |
| IRB-TPL-001 | Job Safety Analysis This template is used by the crew to break a task into steps, identify the hazards of each step and record the controls | Template | Quality and Safety Manager | 2.1 | 18 March 2027 |
| IRB-TPL-002 | Toolbox Talk Record This template records the daily pre-start and weekly toolbox talks held at each site, the topics covered, the issues rai | Template | Fabrication Supervisor | 1.4 | 12 August 2027 |
| IRB-REG-001 | Welding Procedure and Welder Qualification Register This register lists the qualified welding procedure specifications held by Ironbark Engineering and the welders qualifie | Register | Quality and Safety Manager | 3.0 | 30 January 2027 |
| IRB-PLN-001 | Mount Errol Quarries October Shutdown Plan This plan sets out the scope, crew, sequence, permits, materials and safety controls for the seventy-two hour planned sh | Plan | Maintenance Services Manager | 1.2 | 28 February 2027 |